CMRL completes Kathipara balanced cantilever viaduct
According to the latest updates, Chennai Metro Rail Limited (CMRL) has finished the balanced cantilever viaduct at Kathipara Junction on the Phase II Koyambedu to Alandur stretch, The Hindu reported on 27 November 2026. Balanced cantilever is a method where the deck is built outwards from each pillar in matching segments, so no heavy lifting is needed over traffic. The 413 metre curved span runs from Paul Wells Road to Alandur over the cloverleaf flyover and both Phase I corridors, on pillars between 88 and 108 feet tall. Track work has begun and should take 45 days, and officials hope to start train trials by early January.
This is significant as the span was due for completion in February 2026, and its delay has held up the 14.5 km Koyambedu to Alandur section of Corridor 5, which runs from Madhavaram to Sholinganallur. Once the section opens, which officials expect in March 2027, six trains could pass through Kathipara at the same time across two Phase I lines and one Phase II line. Officials said crews could work only from midnight to 4 am, when Phase I overhead power was switched off.
We believe that finishing the hardest structure on this stretch removes the main risk to the March 2027 target, but it does not guarantee it. The four-hour nightly window shows how building next to a live metro slows work, and track laying and systems testing near the same lines will face similar limits. Commuters in western Chennai gain a new route between Koyambedu and Alandur, while the Alandur interchange may see heavier crowds at peak hours. We expect CMRL to run its first test train over the Kathipara span by 31 January 2027, given the 45-day track schedule, and to seek safety clearance for the section by March 2027.
This is important for our readers because the new link will change travel options around Guindy and Alandur in 2027. If you commute through Kathipara Junction, follow CMRL notices this week for any night closures during track work. If you run a business near the Koyambedu to Alandur stations, start planning now for higher footfall from early 2027.
Sources:
The Hindu, 27 November 2026, thehindu.com.
Image used just for representational purposes. It may, or may not, have any relevance to the story.